Street and Pedestrian Lighting

Purpose

To provide requirements for streetlight construction projects.

Who Must Comply?

Streetlight projects located in the franchise area within the geographical boundaries of the City and County of San Francisco

cropping of a map

View an interactive map of streetlights owned by the SFPUC in San Francisco.
 

To report streetlight outages, please call 3-1-1.

To report an emergency situation, please call 9-1-1.

We are here to help developers understand the street and pedestrian lighting requirements and processes in the City and County of San Francisco. Please contact the streetlight engineer reviewing your project for the most up to date information. Please note that drawings provided are markups approved for current use.

street light being repaired with Bay Bridge in the background

General steps for successful installation of streetlights

For more detail, please refer to Streetlight Standards and Requirements. 

  1. Project owner fills out Streetlight Review Request.
  2. SFPUC will review photometrics and work with the Project Owner to establish streetlight locations, pole types and luminaire types. Please reference below for SFPUC approved catalog streetlight materials.
  3. Apply for new unmetered service(s) or request to use an existing service.
    Please see streetlight guidelines for directions on how to apply and/or request to use an existing service.
  4. Project owner will revise streetlight plan to include service point information  
  5. SFPUC will work with the Project Owner to review and approve the streetlight plans. 
  6. SFPUC will issue a Streetlight Inspection Service estimate.
    Estimates will eventually move towards a fee-based system and will collect funds through CSB.
  7. Project owner submits Streetlight Inspection Service fees.
    Please note that Streetlight Inspections cannot be scheduled until payment is provided.
  8. Project owner fills out Inspection Request Form.
    Send at least 15 business days before to schedule an inspection of: a) All streetlight infrastructure before pour and b) Final inspection
  9. The project owner receives an approval of the above from PUC inspector. (email is OK)
  10. The project continues with the construction of the foundation, installation of poles and lights and all other items as necessary.
  11. Project owner submits an Inspection Request Form to request a Final Inspection.
    Streetlights should be installed and operational. Sidewalk should be finished.
  12. SFPUC will provide punchlist items to the Project Owner
  13. Project Owner will address punchlist items.
    Project Owner will also provide as-builts, final submittals, and warranty information to SFPUC.
  14. SFPUC will provide a Notification of Streetlight Acceptance for the Project Owner.
    This notification indicates that the SFPUC will close the streetlight improvement portion of the project and indicates that streetlight ownership and maintenance responsibilities for the new streetlights have been accepted by the SFPUC.

Applications

Have you have collected and submitted all the information needed for review?

Questions?

SLEngineering@sfwater.org - Streetlight engineering related inquires
SLInspections@sfwater.org - Inspection requests
PEMA@sfwater.org - General streetlight related inquiries, as-built inquiries, and redlined drawings

 