The San Francisco Public Utilities Commission (SFPUC) has dozens of projects currently in the works or recently completed – from small sewer repairs to major treatment plant upgrades – that improve the city’s ability to manage stormwater. Combined, these projects total billions of dollars.
San Francisco, like many major cities in the country, operates a combined sewer system designed to collect and treat both sewage and stormwater runoff. Because the system handles both sewage and stormwater, upgrades we are making directly support and enhance the city's ability to manage heavy rain and reduce the risk of flooding during severe storms. Investments across San Francisco's sewer system are ensuring that we are ready for winter storms as well as the next earthquake.
Here are just some examples of projects underway or recently completed:
Treatment Plant Peak Wet-Weather Capacity & Resiliency Upgrades
During intense winter storms, the city's treatment plants must process hundreds of millions of gallons per day of combined sewage and stormwater.
- Major construction is underway to rebuild and upgrade critical components of the City’s largest treatment plan, the Southeast Treatment Plant in the Bayview neighborhood, while keeping the plant running at the same time.
- The recently completed New Headworks Facility Project ($717 million) at that plant handles the first step of the treatment process. It provides all-weather, up-to-250-million-gallons-per-day preliminary treatment by removing trash and grit. It provides state-of-the-art odor control and protects downstream plant operations from heavy storm grit and debris washing off city streets.
Major Sewers and Stormwater Tunnels
These large-scale capital investments enlarge underground sewer capacity, create dedicated storm diversion tunnels, and eliminate hydraulic chokepoints in low-lying, flood-prone neighborhoods.
- The SFPUC completed the Wawona Area Stormwater Improvement Project and Vicente Street Water Main Replacement Project in 2024. This project expanded the stormwater capacity in the low-lying 15th and Wawona area by increasing the capacity of the storm drains and installing a large underground tunnel to expand stormwater conveyance out of the area during heavy storms.
- In November 2026, the SFPUC completed sewer and water system upgrades on Geary Boulevard ahead of schedule. The project replaced aging sewer and water pipes along Geary Boulevard from Stanyan Street to 32nd Avenue. Approximately 1.4 miles of sewer pipes were replaced or rehabilitated, and new sewer structures were constructed. These improvements strengthened the long-term performance of our systems. Sewer upgrades increased the amount of wastewater the system can handle, helping reduce the risk of flooding and sewer backups.
- The Channel Force Main Intertie Project: the Channel Force Main is a massive sewer pipe over five feet in diameter and a mile long that transports wastewater from northeastern San Francisco to the City's largest wastewater treatment plant. It is almost always in use. The project has installed a new pipeline connection and controls to allow parts of the force main to be shut down for maintenance and repair. This will ensure it continues to function for decades to come and can better handle runoff from extreme storms. The project is slated to be completed next year.
- The SFPUC has started construction on the Folsom Area Stormwater Improvement Project and have completed the design for the Lower Alemany Area Stormwater Improvement Project.
Green Infrastructure & Stormwater Runoff Reduction
Green infrastructure projects divert, capture, and slow down stormwater before it can enter the combined sewer system, preserving system capacity during storms conditions. Examples include rain gardens, living roofs, and permeable pavement. This reduces flooding, helps keep our waterways cleaner, and adds more green space to neighborhoods.
San Francisco is on track to meet an ambitious goal: capturing 1 billion gallons of stormwater each year using green infrastructure by the year 2050. So far, San Francisco has built or initiated 575 green infrastructure projects that will capture more than 333 million gallons of stormwater in total each year when completed.
- The completed Sunset Boulevard Greenway constructed rain gardens across 10 to 16 blocks along Sunset Boulevard.
- Projects like the Alemany and Cayuga Greening, in partnership with the San Francisci Municipal Transportation Agency (SFMTA), are targeting 65 acres of drainage management area to divert 35 million gallons of stormwater annually away from the sewer system.
- The Green Infrastructure Grant Program provides grants to large private and public properties across San Francisco to build rain gardens, permeable pavement, cisterns, and green roofs, suppressing peak stormwater runoff. Since 2019, the SFPUC has given $32.7 million in grants to schools, health care facilities, arts organizations, and other property owners to build these kinds of projects.
Pump Station Upgrades & Force Main Reliability
Pump stations are mechanical lifelines during storms, lifting wastewater and collected stormwater out of low-lying basins and driving high-volume flows toward treatment plants or deepwater outfalls.
- The North Shore Wet Weather Pump Station Improvements completed a major overhaul of the critical wet-weather facility along the northern waterfront, which can handle 150 million gallons per day during storms. The project replaced pumps and improved operational redundancies to ensure continuous maximum pumping throughput during major storms.
- Work is underway on the Westside Pump Station Reliability Improvements to fortify the primary west-side pump station and to provide operational flexibility and redundancy to this critical facility that serves the west side of the City.
Combined Sewer Discharge Outfalls, Backflow Prevention & Storage Structures
San Francisco's combined system includes large transport/storage boxes ringing the shoreline that can hold a total of nearly 200 million gallons of wet-weather flows. When storage fills during severe atmospheric rivers, permitted combined sewer discharge outfalls release excess partially treated stormwater into San Francisco Bay and the Pacific Ocean.
- Projects recently completed or underway include upgrades to the outfalls at Evans Avenue, Laguna, Brannan, Mariposa, Howard, Sansome, and multiple locations at Mission Creek.
Renewal & Replacement Program
In addition to major capital projects, the SFPUC Wastewater Enterprise executes an ongoing, annual Renewal and Replacement Program targeting the most at-risk pipes, localized flooding spots, and plant components across the city.
- With annual budgets over $100 million per year for the next two years, these sewer upgrades repair and replace neighborhood street mains, laterals, and catch basins, ensuring local street runoff drains into the trunk sewers without backing up. There are currently 24 projects in construction, 12 in construction procurement, and 38 in design.
Floodwater Grants
The Floodwater Grant program provides up to $100,000 to fund approved flood protection projects, such as flood barriers, sump pumps, and sewer backwater valves, for eligible properties that have experienced flooding from the public right of way or the City sewer system during heavy rains. The SFPUC has awarded nearly $1.7 million over the life of the program.